IE Rules for DP Structure
Indian Electricity Rules for Double Pole Structure(D.P):
IER-61-2.
Only one connection with earth has been provided for the frame of A B switch. One more Separate and Distinct connection with earth should be provided for frame of the A B switch.
IER-61-2.
Only one connection with earth has been providing for the frame of the H G fuse. One more Separate and distinct connection with earth should be provided for the frame of HG fuse.
IER -29&5b.
The metal cover of the transformer (top cover) on which the HV and or LV busing are Housed should be Looped to earth to avoid any fault current passing through fastening bolts.
IE R-9 2.
The earthling lead of the HV lighting arrester is not kept separate but it mixed with other Connections. The earthling lead from the HV lighting arrester should not be used for earthling Any other gear and should be taken to a separate electrodes.
IER-51-1 b & 61 -3.
The GI pipe enclosing the MV circuits on the secondary side of the transformer are Not earthed. This should be earthed.
IER- 29&9 2.
The earth lead from the HV lighting arrestor is taken through GI pipe. The above earth lead Should not Pass through any iron steel pipes.
IER 29&51b
The AB switch handle has not been earthed. The same should be earthed effectively.
IER-29
Masonry through are not provided for the earth electrodes. Masonry through should be Provided for the Earth electrodes.
IER -29.
No name board has been provided for the substation. A name board with all particulars Should be providing.
IER 50 1 b.
There is no fuse control on the secondary side of the transformer but only the outgoing Feeders are provided with fuse control. Porcelain fuse unit of adequate capacity should be Provided for the transformer on the secondary side and only from these fuse unit supply to the outgoing feeders should be tapped.
IE R-29.
The handle of the AB switch has been fixed at a height of about 4-5 feet’s for easy operation.
IER 29.
The UN supported length of jumper in the transformer structure is more than5 feet. The same Should be restricted to a length of 5feet.
IER 51 1a & b
All the open wiring on the secondary side of the transformer should be closed in conduits.
IER 29.
The secondary control of porcelain fuse carrier is not housed in distribution box. They should Be housed in the distribution box No breather has been provided for the transformer a breather should be provided for the transformer.
IER 29.
Some of the fuse units are broken. The broken fuse units should be replaced by fresh unit.
IER 50 1b.
The feeders emanating from the secondary fuse control are not provided with separate fuse Unit individually. Further one feeder is tapped from another. There should not be any tapping In the feeder and the entire emanating feeder should be provided with fuse units individually.
IER 51 -1b
The providing pipe of the AB switch has not been earthed. The same should be earthed Effectively.
IER 91 .
Earthed called guarding has not been provided at the place where the HV/MV lines are Crossing the road. Suitable earthed cradle guarding should be provided for the road crossing.
IER 29.
The metal parts of the DP structure distribution box have rusted badly and requires Repainting. Repainting should be carried out to the above structure and should be maintained Properly.
IER 29.
All the routine maintenance work on the transformer like testing of transformer oil etc should Be periodically and the result obtained should be recorded up to date in a separate register.
IER 29 & 61 b.
The earth electrodes provided should be tested periodically for satisfactory results and Results obtained should be recorded up to date in a separated register.
IER 29.
The HV jumpers connected on the tension side are to be connected to the slack side or U Loop connection on the line.
IER29
No HV /LA (Lighting arrester) is provided for the protection of the transformer which should Be provided..
IER 51 -1b.
The metallic fittings of the insulators, strain dishes are to be looped to earth leads of Structure
IER 29
Bushes are not provided for the ends of conduit pipes enclosing MV wires on the secondary Sides. Bushes are to be provides for the ends of conduit pipes.
IER 29.
The insulated wires on the secondary side of the transformer are deteriorated and they Should be replaced by healthy wire
IER 35.
Danger notices have been provided the transformer section. Danger notice is to be provided For the transformer section.
IER29.
Oil leak in the LV bushing of the transformer should be attended.
IER29.
The position of the HV/LV is to be shifted to the other side so that the clearance between The live jumper and earthed metal parts should not less than12 inches.
IER 29.
The transformer base channel from ground is less than 7 feet and the clearance to HV live Point from ground is less than 12 feet. The above clearances are to be provided
IER 61-1a.
The transformer neutral is provided with only one earthy. The neutral should be provided With one more earth connection.
IER 61 -1a.
The transformer neutral earth lead is looped with body. The neutral earth leads should be Separated from the transformer body
IER 61 -2
The transformer body is earthed with signal earth connection. The transformer body should Be provided with two separate and distinct earth locations.




Dear jigneshbhai,
I am doing electrical project work in gujarat and i have a also require electrical specifitation As per IE/CPWD for Earthing work, cablling work,lighting work,two pole eraction work.
Pls send a specification,by mail.
smit.electricals@gmail.com
Thanks
shailesh prajapati
09898597481. kindly give your email, mobile no.
Dear sir,
Kindly send me the details@ Mim.Dist. required betwn two near by transformer of 500KVA as per IE rules.
As per guidelines are from IEEE 979 for liquid-filled transformers for Outdoor Purpose.
7571 liters or more of oil – 20 feet from building, if 20-50 feet from building, the exposed walls of the building should have a 2 hour fire barrier.
75 kVA or less – 10 feet from building.
76-333 kVA – 20 feet from building.
More than 333 kVA – 30 feet from building.
Add fire barriers if above minimums aren’t maintained.
Large oil-filled transformers should be separated by at least 30 feet of clear space and/or a minimum 1 hour fire rated barrier.
the minimum distance3 between any two electrical carrying equipments is 2.5 mtr .it is advised
to have 3.5 m distance between centre to centre of transformer 500 kva equipment
Regarding allowable Earthing values as per IE Rules, we require authentic information.
The dimensional details of various installations of Electrical System as per IE Rules is requested.
Sir
Sir can you suggest me new electrical technologies or equipments or energy saving methods prevailing in Power plants. As i work in Knowledge Management deptt. , as my profile is to search new kind of technologies which is cost effective and energy efficient.
Regards
Sharad Goyal
Sir,
I am working in IRCON at Malaysia, sir we are facing one problem in our circuit. We have a cast rasin Aux. trf. of rating 20kVA for Aux supply of our switching station. primary Voltage of Trf. is 25kV single phase and secondary voltage is 240V there is no tap changer. When we put load on Aux. trf. it gives humming sound and voltage flctuate from 240V to 260V. Also current becomes higher. We observe that only one tube light takes 20A current for some second in the mean time the MCB of light trip. We also observe that when there is train movement at that time there is variation in voltage as well as in current. Connection of our taf. is as follows we connect neutral of Trf to ground Primary side and secondary side also through return bar.
can u suggest some idea to stable the voltage.
Thanks
Can I have detailed dimensional Drawing for D. P. Structure for 11kV to 33kV system.
sir could u send the detail about substation SLD to end design (33kv,132kv,110kv,66kv)
i want dimensional detail about installed difference between two equipment, ratings,LM tower detail etc
sir
what is difference between earthed and unearthed HT cable?
Please send me details regarding DP -one pole earthing and one separate handle earthing.
with picture to my mail id sunil_asvee@yahoo.co.in
sunil rathod