Sub Station Abstracts
June 8, 2011 15 Comments
Sub Station Equipments and Safety Clearance
Rating of Lighting Arrestor:
- Size of L.A = 1.5 X Phase to Earth Voltage OR
=1.5 X system Voltage/1.732 OR
= 0.81 X highest System Voltage
Lighting Arrestor Protection Radius:
- Protection Radius (Rp) = Sqrt (H X (2D-H)+L(2D+L))
H= Actual Height of L.A
D= 20 meter, 40 meter or 60 meter
L= V X T (T=Discharge Time & V= 1m/ms)
Creepage Distance:
- 18 mm to 22 mm /KV for Moderate Polluted Air.
- 25 mm to 33 mm /KV for Heavily Polluted Air.
- In HVDC System The value is double from above value.
Lighting Arrestor Rating:
|
Rated Voltage |
Highest Voltage |
L.A Rating |
|
132kv |
145kv |
120kv To 132kv |
|
220kv |
245kv |
198kv To 216kv |
|
400kv |
420kv |
336kv |
Location of Lighting Arrestor:
|
Rated Voltage |
Max Distance from Equipment |
|
132kv |
35 meter To 45 meter |
|
220kv |
Closed To Transformer |
|
400kv |
Closed To Transformer |
Size of Corona Ring:
|
Rated Voltage |
Size of Corona Ring |
|
Less than 170 KV |
160mm Ring Put on HV end |
|
170KV To 275KV |
350mm Ring Put on HV end |
|
More than 275KV |
450mm Ring Put on HV end |
|
More than 275KV |
350mm Ring Put on HV end |
Capacity of Sub Station as per GERC:
|
Size of S/S |
Electrical Load |
|
66 KV |
80 MVA |
|
132 KV |
150 MVA |
|
220 KV |
320 MVA |
|
400 KV |
1000 MVA |
Breaking / Short Circuit Capacity of Sub Station:
|
Size of S/S |
Short Circuit Current |
|
66 KV |
25 KAmp for 1 or 3 sec |
|
132 KV |
31.5 KAmp for 1 or 3 sec |
|
220 KV |
40 KAmp for 1 or 3 sec |
|
400 KV |
40 KAmp for 1 or 3 sec |
Fault Clear Time:
|
Size of S/S |
Fault Clear Time |
|
66 KV |
300 mili Sec |
|
132 KV |
160 mili Sec |
|
220 KV |
120 mili Sec |
|
400 KV |
100 mili Sec |
Normal Type of Conductors:
|
Voltage |
Main Bus |
Auxiliary Bus |
|
11KV |
Twin ACSR Zebra |
ACSR Zebra |
|
33KV |
ACSR Zebra |
ACSR Zebra |
|
132KV |
ACSR Zebra |
ACSR Panthers |
|
220KV |
Twin ACSR Zebra |
ACSR Zebra |
|
400KV |
1/14.2 mm Dia Alu Pipe |
Twin ACSR Moose |
Number of Disc Insulator:
|
System |
Number |
Strength (KN) |
|
11KV |
4 |
120KN |
|
33KV |
4 |
120KN |
|
132KV |
10 |
120KN |
|
220KV |
14 |
70KN |
|
220KV (Anti Fog) |
2 X 15 |
120KN |
|
400KV (Anti Fog) |
2 X 25 |
120KN |
Minimum Clearance:
|
Voltage |
Phase to Earth Wire |
Phase to Phase |
Section Clearance |
|
2.2KV |
28cm |
33cm |
27.45cm |
|
33KV |
380cm |
43cm |
27.7cm |
|
132KV |
107cm |
12cm |
25cm |
|
220KV |
178cm |
20.6cm |
42.8cm |
|
400KV |
350cm |
40cm |
65cm |
Ground Clearance:
|
Voltage |
Meter |
|
33KV |
3.7meter |
|
66 KV |
6.1meter |
|
132 KV |
6.1meter |
|
220 KV |
7.0meter |
|
400 KV |
8.8meter |
Conductor Spacing:
|
Voltage |
Highest Voltage |
Lighting Impulse Level (Kvp) |
Min Clearance |
Ground Clearance |
Safety working Clearance |
|
|
Phase to Earth |
Phase to Phase |
|||||
|
11KV |
12kv |
70 |
178mm |
229mm |
3700mm |
2600mm |
|
33KV |
36kv |
170 |
320mm |
320mm |
3700mm |
2800mm |
|
132 KV |
145kv |
550 |
1300mm |
1300mm |
4600mm |
3700mm |
|
220 KV |
245kv |
950 |
2100mm |
2100mm |
5500mm |
4300mm |
|
400 KV |
420kv |
1425 |
3400mm |
4200mm |
8000mm |
6400mm |
Earthing Resistance Value:
|
Particular |
Max Earthing Resistance |
|
Power Station |
0.5Ω |
|
EHT Sub Station |
1Ω |
|
33KV Sub Station |
2Ω |
|
Double Pole Structure |
5Ω |
|
Tower foot Resistance |
10Ω |
|
Distribution Transformer |
5Ω |
|
220KV Sub Station |
1Ω To 2Ω |
|
400KV Sub Station |
0.5Ω |
Losses in 11 kv Transformer at 75c (As per CBIP):
|
Transformer |
No Load Loss(kw) |
Load Loss (kw) |
% Impedance |
|
3.15MVA |
2.9 |
20 |
6.25 |
|
4MVA |
3.2 |
27 |
7.15 |
|
5.3MVA |
3.9 |
31 |
7.15 |
|
6.3MVA |
4.5 |
37 |
7.15 |
Losses in 66 kv Transformer at 75c (As per CBIP):
|
Transformer |
No Load Loss(kw) |
Load Loss (kw) |
% Impedance |
|
6.3MVA |
6 |
40 |
8.35 |
|
8MVA |
7.1 |
48 |
8.35 |
|
10MVA |
8.4 |
57 |
8.35 |
|
12.5MVA |
9.7 |
70 |
8.35 |
|
20MVA |
13 |
102 |
10.0 |
Standard Rating of 66KV Transformer (As per CBIP):
|
Transformer |
KV |
Type of Cooling |
|
6.3MVA |
66KV/11KV |
ONAN |
|
8MVA |
66KV/11KV |
ONAN |
|
10MVA |
66KV/11KV |
ONAN |
|
12.5MVA |
66KV/11KV |
ONAN / ONAF |
|
20MVA |
66KV/11KV |
ONAN / ONAF |
% Impedance for Transformer (As per IS 2026):
|
33KV Transformer |
66KV Transformer |
||
|
MVA |
%Impedance |
MVA |
%Impedance |
|
1MVA |
5% |
6.3MVA |
8.35% |
|
1.6MVA |
6.25% |
8MVA |
8.35% |
|
3.15MVA |
6.25% |
10MVA |
8.35% |
|
4MVA |
7.15% |
12.5MVA |
8.35% |
|
5MVA |
7.15% |
20MVA |
10% |
|
6.3MVA |
7.15% |
16MVA |
10% |
|
8MVA |
8.35% |
25MVA |
10% |
|
10MVA |
8.35% |
31.5MVA |
12.5% |
|
MVA |
%impedance |
|
Less Than 1MVA |
5% |
|
1MVA To 2.5MVA |
6% |
|
2.5MVA To 5MVA |
7% |
|
5MVA To 7MVA |
8% |
|
7MVA To 12MVA |
9% |
|
12MVA To 30MVA |
10% |
|
More Than 30MVA |
12.5% |
Bus Bar Materials:
| Description | Bus Bar and Jumper Material |
| 400 kV Main Bus | 114.2 mm dia. Aluminium pipe |
| 400 kV equipment interconnection | 114.2 mm dia. Aluminium pipe |
| 400 kV overhead bus & droppers in all bays. | Twin ACSR Moose |
| 220 kV Main Bus | Quadruple / Twin ACSR Zebra / Twin AAC Tarantulla |
| 220 kV Auxiliary Bus | ACSR Zebra |
| 220 kV equipment interconnection | Twin ACSR Zebra / Single ACSR Zebra |
| 220 kV overhead bus & droppers in all bays. | Twin ACSR Zebra / Single ACSR Zebra |
| 132 kV Main Bus | ACSR Zebra |
| 132 kV Auxiliary Bus | ACSR Panther |
| 132 kV equipment interconnection | ACSR Zebra / ACSR Panther |
| 132 kV overhead bus & droppers in all bays. | ACSR Panther |
| 33 kV Main Bus | ACSR Zebra |
| 33 kV Auxiliary Bus | ACSR Zebra |
| 33 kV equipment interconnection, overhead bus and droppers: | |
| (i) Bus coupler & transformer bay | ACSR Zebra |
| (ii) Feeder bay. | ACSR Panther |
| 11 kV Main Bus | Twin ACSR Zebra |
| 11 kV Auxiliary Bus | ACSR Zebra |
| 11 kV equipment interconnection, overhead bus and droppers: | |
| (i) Transformer bay | Twin ACSR Zebra / Single ACSR Zebra |
| (ii) Bus coupler | ACSR Zebra |




Thank u very much for providing valuable material. It is very helpful to me.
Thanks for this upload
Thanks a lot Mr: Jignesh. The datas was very helpful
Asif KM
Saudi Electricity Company
very very good!!!
very helpful..
I have request could you please provide the standard/code reference for Earthing Resistance Values.
Thanks in advance.
Earthing Resistance Value:
Power Station = 0.5 ohm.
Sub Station Major=1.0 ohm.
Sub Station Minor=2.0 ohm.
Distribution T/C=5.0 ohm.
Transmission Line=10 ohm.
As per My knowledge.There is not exact value for Earthing Resistance in any Standard ,It depend upon Soil but There is a guideline in Some Code that it should be less than 5 ohm and in some code it is given less than 10 ohm.
hi!
i want know how to calculate the LA (lightining Arrestor) rated voltage.
any formula
Would you please to told me what’s meaning GERC and CBIP??
Thanks a lot
GERC =Gujarat electricity Regulation Commission
CBIP=Central Beau of Irrigation and Power
Its very good. Thank you very much.
could i get a detailed article on power transformer testing including the purpose
hi
VERY INFORMATIVE .PLEASE PROVIDE INFORMATION ABOUT PROTECTION DIAGRAMS
Dear Sir , we are thankful to you for the exhaustive information u provide in collective manner. Pl provide some article on DC Battery chargers & DC Batteries used in EHV sub stations.